Provo City Airport Pump Station

Provo City Airport Pump Station

Santaquin City Hall

This project is to construct a new City Hall on the corner of 100 South and Center Street in Santaquin City. This structure will have 2 floors in the east & west wing, the main building will have 3 floors all together it has 47,957 sq ft. The basement contains rooms for the emergency operation center, storage rooms, record room, mechanical room, electrical room, server room. Break room with kitchen, restroom & offices. The main level has 20,284 sq ft. The west wing is unfinished and the east wing has the multipurpose room,  kitchen and restrooms. The main building’s main floor has offices, conference rooms, council chamber, restrooms and storage rooms The Upper lever has 5710 sq ft with offices, conference rooms,  storage and restrooms.

Provo Southwest Lift Station

The construction of this project includes the excavation, dewatering, necessary shoring, grating, yard piping, wet well and dry pit concrete structures; Building construction including concrete, CMU, plumbing, electrical, and HVAC, piping, and standby generator; dry-pit submersible pump station, including suction and discharge piping and instrumentation; and site improvement including pavement, driveway, drainage improvement, and perimeter fencing with access gate. Splitter box,  pump station dry pit, and wet wells will be constructed of the cast in place concrete. The electric building will be constructed of CMU and will be the only above-ground structure. Construction will include installing (3) pumps in this phase while allowing for the future.

JVWCD Chlorination Booster Buildings

This project has two sites the first is Rosecrest Reservoir the other is 9800 South Reservoir purpose of this project is to replace the portable chlorination trailer that the district has been using with a new permanent chemical feed facility at each site. Along with a Flow Meter at each site.

DFCM 13.04 Water Tank & Pump Station

Construction of a drinking water pump station building, 0ne 1.5 million gallon tanks, all associated, 2-75 hp and 2- 20hp pumps and drives, 800amp ATS power distribution, instrumentation, and chlorination room.

 

Gunlock WTP

The work consists of construction of a new 6 million gallon per day arsenic

treatment facility with all related components, including a treatment building

containing horizontal pressure vessels, chemical systems (including tanks, pumps

and equipment), backwash clarification tanks, pump enclosure, solar drying beds,

piping, paving, pumps, security fencing, and other associated components.

 

高仿勞力士
lignnone size-medium wp-image-693″ src=”https://morrisele.com/wp-content/uploads/Gunlock-Chlorine-Room-1-300×225.jpg” alt=”” width=”300″ height=”225″ />

Sandhollow WTP

The work consists of construction of a new 3 million gallon per day arsenic treatment facility with all related components, including a treatment building containing a horizontal pressure vessel (and space for a future vessel), chemical systems (including tanks, pumps and equipment), backwash clarification tank, pump enclosure, solar drying beds, piping, paving, pumps, security fencing, and other associated components.

 

壯陽藥
-medium wp-image-688″ src=”https://morrisele.com/wp-content/uploads/Under-Slab-2-1-225×300.jpg” alt=”” width=”225″ height=”300″ />

Springville WRF 2020 Upgrades

The work consists of site demolition and removal of existing equipment, structures. Construct a building and storage area to house a new primary chemical storage tank and chemical dosing pumps adjacent to the existing headworks building. Install new secondary chemical dosing pumps in the existing belt press building. Installation of a secondary chemical dosing. Construct a new DAFT building and install owner furnished HUBER DAFT equipment package DAFT building includes a new electrical room.

 

DFCM 13.04 Pump Station #1

Construction of a sanitary sewer pump lift station. With a 2000/3 Service, 750kva Generator, 2000amp ATS, Distribution Panel, One 335 hp pump with VFD and two- 85hp pump with VFD. Along with all the instrumentation and controls. This also includes a grinder vault with two grinders, a Metering, a Pigging, and Flushing building.